E&S engineering of Hou Li Extra High Voltage substation Introduction Introduction: Location: No. 17-50, Yongxing RD., Houli District, Taichung City CHEM contracts this project based on the turn-key basis, the scope of supply are: Power Transformation Portion: To set up the brand-new 161kV GIS and the relative equipment. Main equipment: 161kV GIS: 2000A IC50kA 1set 69kV GIS on the thirdly side of autotransformer 161kV、69kV、25kV XLPE power cable & 600V control cable Battery & Charger: DC 125V 260AH 2sets, DC 125V 75A Charger 5sets, DC 48V 800AH Charger ( 2N+1 ) 1set SSTR: 1000kVA 2Sets Cable tray 1 set SCADA system include RTU、UPS etc BACK ↑TOP